Turner Construction Caught Up In New York City Cost Dispute

Text size: A A

New York City's Economic Development Corp. has reacted strongly to a new audit by the city comptroller that says the agency allowed locally-based Turner Construction Co. to rack up more than $3 million in "dubious" payments on a construction and facilities management contract.

----- Advertising -----

The comptroller says the contract had ballooned to nearly $74 million from $7.5 million in three years. It involved a variety of projects, including a garage and pedestrian protection during pier repairs.

"We are disappointed that after a 16-month review, the Comptroller's Office has issued an audit report that is flawed, misleading and draws unsupported conclusions,” said EDC in a written statement.

The EDC statement said that “20 of the 21 completed projects included in this audit came in under budget-for a net aggregate savings of $2.7 million."

City Comptroller John Liu seems to have anticipated that his 86-page audit, released last month, would set off a firestorm. The lengthy document, which includes EDC responses to every recommendation, acknowledges that there is extensive disagreement in the "amount of opposing detail now included in this report."

Yet the controversy seems to have overshadowed the contents of the audit, including the construction projects criticized and allegations by. Liu that years of EDC inaction on construction hazards endangered public safety in three instances.

The audit states that Turner was overpaid on a number of municipal projects, and criticized the contractor, and EDC, for inaccurate installations, "poor quality work" and "incorrect labor rates."

The audit alleges "[u]nnecessary costs for material loading, storage and transportation," the installation of temporary roofing, insurance paid prior to work cancellation and "[e]xcessive construction management costs," totaling more than $1.4 million.

The comptroller also claims there was a lack of pre-payment auditing, improper reimbursement, poor documentation and improper use of allowance, totaling close to $1.8 million.

The audit offers 31 recommendations on how EDC can resolve "significant weaknesses" of its contract oversight, 19 of which the corporation said it was already complying with. However, it disagreed wholly or partially with nine recommendations and emphatically denied that its actions “endangered public safety."

But Liu was unmoved. “In these cases, the Corporation's belated approach for compelling Turner to undertake critical and timely repairs of city facilities indicates [its] lackluster approach in providing effective oversight and monitoring," the audit states.

EDC claims that the positive results of municipal projects it managed “speak for themselves," but the audit contends the agency “cannot absolve itself from its overall [contract management] responsibility."

A Turner spokesman said that the company has complied fully with the audit and cooperated with the EDC.

“While EDC has provided a full response to the Comptroller's report, we can reiterate that Turner's "on-call" facility management and construction management services are being performed with a full-commitment to quality, safety and integrity,” says a company statement. “With the established ‘on-call’ agreement we have with the EDC, we are able to quickly mobilize staff and resources to respond to their needs as projects are identified and funds are made available.”

This story has been revised at 12:25pm on March 4, 2011.

 

----- Advertising -----
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.