The fabric roof of the Metrodome Stadium in Minneapolis collapsed on Dec. 12 under the weight of 17 or more inches of wet snow. Steve Maki, the stadium’s director of facilities and engineering, said a seven-person snow-removal crew retreated from the roof when winds gusting to 40 mph made working unsafe. Maki says that, early Sunday morning, one fabric roof panel gave way because of the snow load, which overstressed two more panels that also then failed. The roof was fabricated and installed by Birdair Inc., Amherst, N.Y., in 1981. Maki says three samples of roof fabric tested early last spring still rated above the original specifications after nearly 30 years.


Sign in to Comment
To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.