subscribe to ENR magazine subscribe
contact us
advertise
careers industry jobs
events events
FAQ
Mcgraw Hill Construction
ENR Logo
SUBSCRIBE TODAY
& receive immediate web access
comment

Best Airports/Transit Project

Text size: A A
Photos courtesy of Reynolds, Smith and Hills
Mid-Atlantic Regional Spaceport Pad-0A in Wallops Island, Va.
----- Advertising -----

The first launch pad in the U.S. to be built specifically as a multi-user facility to accommodate rockets from private companies, the Mid-Atlantic Regional Spaceport Pad-0A in Wallops Island, Va., enables continued space exploration and aims to foster the development of the commercial space transportation industry.

Located at the Mid-Atlantic Regional Spaceport on a narrow Virginia barrier island, the project created the most compact launch site ever designed for a medium-class, liquid-fueled launch vehicle, project officials say. Commodity tanks, a water tower and a deluge water-retention pond had to be located closer to the pad than usual, heightening safety concerns over anticipated launch loads. To address the issue, the team added blast-protection structures and hardened the buildings.

For decades, launch pads have used the same type of refractory concrete to protect the flame deflector and adjacent structures. On this project, however, the team selected materials—Sentinel RC and HP Cast 93Z, developed by Harbison-Walker—that provided the required protection while reducing costs.

The limited site area also required an innovative approach to the facility's lightning protection system. While other launch facilities use a standard guy-wire-and-tower system, the Pad-0A team designed a more compact system using steel poles that usually are used to support lights at highway interchanges. This tactic required further coordination with the pole manufacturer as well as testing to ensure the poles were strong enough to withstand blast loads. The solution significantly trimmed construction costs and saved time.

Since the site was located less than 25 ft from the seawall—closer than any other launch facility—the team had to raise the floor elevation to prevent flooding.

Faced with a fast-track schedule, the design team needed to release incremental design packages so the contractors could start building facilities. In addition, both the pad and its first launch vehicle were being designed at the same time, requiring collaboration between those teams.

During construction, the site was hit by heavy storms, including Superstorm Sandy. The storms caused severe flooding, but the site remained undamaged, partly because of precautions taken by the contractors.

All contractors attended NASA's Wallops Flight Facility Safety Training and Mid-Atlantic Regional Spaceport's Specific Facility Safety Training classes. Each contractor also submitted a weekly contractor-specific safety plan, along with pertinent operation status information. Open communication allowed team members to provide input on best practices for safety, quality and production as conditions changed.

For the bridge deck that approaches the launch pad, the team developed an approved design to clamp specially made brackets around the piles using clevis hooks to attach retractable tools. The solution was load-tested above Occupational Safety & Health Administration requirements and, ultimately, enabled workers to move freely about the deck without the risk of falls.

The project recorded no lost-time incidents and had an OSHA recordable incident rate of zero.

Mid-Atlantic Regional Spaceport Pad-0A. Wallops Island, Va.

Key Players

Owner Virginia Commercial Space Flight Authority

Design Firm Reynolds, Smith & Hills

General Contractor Baker Concrete

Structural Engineer Reynolds, Smith & Hills

Civil Engineer Reynolds, Smith & Hills

MEP Engineer Reynolds, Smith & Hills

Electrical Engineer Reynolds, Smith & Hills

Keywords:

----- Advertising -----
  Blogs: ENR Staff   Blogs: Other Voices  
Critical Path: ENR's editors and bloggers deliver their insights, opinions, cool-headed analysis and hot-headed rantings
Project Leads/Pulse

Gives readers a glimpse of who is planning and constructing some of the largest projects throughout the U.S. Much information for pulse is derived from McGraw-Hill Construction Dodge.

For more information on a project in Pulse that has a DR#, or for general information on Dodge products and services, please visit our Website at www.dodge.construction.com.

Information is provided on construction projects in following stages in each issue of ENR: Planning, Contracts/Bids/Proposals and Bid/Proposal Dates.

View all Project Leads/Pulse »

 Reader Comments:

Sign in to Comment

To write a comment about this story, please sign in. If this is your first time commenting on this site, you will be required to fill out a brief registration form. Your public username will be the beginning of the email address that you enter into the form (everything before the @ symbol). Other than that, none of the information that you enter will be publically displayed.

We welcome comments from all points of view. Off-topic or abusive comments, however, will be removed at the editors’ discretion.